DATA: Status of Marawi rehabilitation projects as of December 25, 2022

BY PHILIPPINE CENTER FOR INVESTIGATIVE JOURNALISM (PCIJ) March 01, 2023
 
 

 

The rehabilitation work of Task Force Bangon Marawi (TFBM) was 85% complete, according to TFBM Field Office Manager Felix Castro Jr. during a Senate hearing on Feb. 23. 

The projects do not cover private properties. Out of 17,793 households in the "most affected areas" during the siege, only 100 or not even one percent have returned. (READ: Marawi buildings — with a price tag of P10-B — are ready but empty)

The newly constituted Marawi Compensation Board seeks to addres this problem. (READ: All eyes on Maisara Latiph, who will decide compensation of Marawi siege victims)

 

 

 