| Name
of Plant : |
Bauang
Diesel Power Plant Project (A14) |
|
| Name of IPP : |
Bauang Private Power Corporation |
|
| Contract Type : |
Build-Operate-Transfer/Energy
Conversion Agreement/Solicited |
|
| Status of Plant : |
Operating |
|
| Cooperation Period : |
15 years (February 1995 - February 2010) |
|
| |
|
|
| Nature
of Issue |
Issue |
Recommendation |
| Changes to Contract |
Without ICC, approval, the contracted capacity was increased
from 195 MW to 215 MW, allegedly "due to erroneous cover page" and
the Base Capacity Rate was raised from US$14.00 per KW/mo. to US$15.12 per
KW/mo.
|
Legal review required as to validity of amendments. |
| Correction
to the Contract |
This
contract differs from other similar contracts in that the no. 1 is missing in
the F (Outage) Factor definition. BPPC billed NPC for this in the past, but
NPC did not pay.
|
To make
necessary correction in the contract |
| |
The issue
is not currently relevant because of low dispatch factor but NPC needs to
guard against such future claims for the remaining 8 years of cooperation
period. |
|
| |
|
|
| High
Cost of IPP |
BPPC's Cost
(Levelized IPP Cost + Fuel is Php2.791Kwh) ranks no. 15 from overall and 7
from Bunker C type of fuel. |
Review of
possible improvement of fees structure, especially the Operating and
Maintenance Fee (0 & M), considering that the plant is
underutilized.
|
| |
BPPC ranks
no. 2 (in proportion to capacity) in Net loss to NPC due to low dispatch
amounting to Php 5.1 billion. |
|
| |
|
|
| |
Cumulative
Return on Investment is 83% for 6 years of operation. |
|
|
|
|